Building projects
$555.9 million
Exact amount: $555,945,321.00
FY2026 (July 2025–June 2026)
Fixing and building schools. The project list is $3,874 short of the capital fund lines in the budget database, shown below as a visible difference.
Follow the money
Inside this box
Pick a rectangle to see what is inside it. Rectangle area shows positive amounts; the complete list includes reductions and tiny amounts.
On small screens, use the complete linked table below to explore each box.
All items
| Box | Amount | % of this budget |
|---|---|---|
| Facility Needs | $340,746,126.00 | 61.3% |
| IT, Security and Other Projects | $118,515,321.00 | 21.3% |
| Educational Programming | $28,680,000.00 | 5.2% |
| Facility Site Improvements | $28,300,000.00 | 5.1% |
| Capital Project Support Services | $23,000,000.00 | 4.1% |
| Building Interior | $16,700,000.00 | 3.0% |
| Not matched to a listed project · Leftover | $3,874.00 | <0.1% |