Chicago Public Schools

MOSAIC

$8.1 million

Exact amount: $8,080,000.00

FY2026 (July 2025–June 2026)

Roof Renovation. Status: Planning. Paid for by: Needs Assessment.

Explore this flow Search this budget →

Follow the money

Inside this box

Pick a rectangle to see what is inside it. Rectangle area shows positive amounts; the complete list includes reductions and tiny amounts.

Where the positive amounts goEach rectangle’s area is proportional to its amount. Select a region to open its box; the list below includes every amount.
MOSAIC: Construction, $6,423,600.00, open this boxMOSAIC: Construction$6.4 millionMOSAIC: Design, $808,000.00, open this boxMOSAIC: Design$808,000MOSAIC: Project management, $444,400.00, open this boxMOSAIC: Project management$444,400MOSAIC: Environmental review, $404,000.00, open this boxMOSAIC: Environmental review$404,000

On small screens, use the complete linked table below to explore each box.

All items

Percentages of MOSAIC
BoxAmount% of this budget
MOSAIC: Construction$6,423,600.0079.5%
MOSAIC: Design$808,000.0010.0%
MOSAIC: Project management$444,400.005.5%
MOSAIC: Environmental review$404,000.005.0%

Sources