Chicago Public Schools

GRIMES (Mechanical, Electrical & Plumbing Renovation)

$2.7 million

Exact amount: $2,725,000.00

FY2026 (July 2025–June 2026)

Mechanical, Electrical & Plumbing Renovation. Status: Planning. Paid for by: Needs Assessment.

Explore this flow Search this budget →

Follow the money

Inside this box

Pick a rectangle to see what is inside it. Rectangle area shows positive amounts; the complete list includes reductions and tiny amounts.

Where the positive amounts goEach rectangle’s area is proportional to its amount. Select a region to open its box; the list below includes every amount.
GRIMES: Construction, $2,166,375.00, open this boxGRIMES: Construction$2.2 millionGRIMES: Design, $272,500.00, open this boxGRIMES: Design$272,500GRIMES: Project management, $149,875.00, open this boxGRIMES: Project management$149,875GRIMES: Environmental review, $136,250.00, open this boxGRIMES: Environmental review$136,250

On small screens, use the complete linked table below to explore each box.

All items

Percentages of GRIMES (Mechanical, Electrical & Plumbing Renovation)
BoxAmount% of this budget
GRIMES: Construction$2,166,375.0079.5%
GRIMES: Design$272,500.0010.0%
GRIMES: Project management$149,875.005.5%
GRIMES: Environmental review$136,250.005.0%

Sources