Chicago Public Schools
IRVING
$6.8 million
Exact amount: $6,805,000.00
FY2026 (July 2025–June 2026)
Mechanical, Electrical & Plumbing Renovation. Status: Planning. Paid for by: Needs Assessment.
Follow the money
Inside this box
Pick a rectangle to see what is inside it. Rectangle area shows positive amounts; the complete list includes reductions and tiny amounts.
On small screens, use the complete linked table below to explore each box.
All items
| Box | Amount | % of this budget |
|---|---|---|
| IRVING: Construction | $5,409,975.00 | 79.5% |
| IRVING: Design | $680,500.00 | 10.0% |
| IRVING: Project management | $374,275.00 | 5.5% |
| IRVING: Environmental review | $340,250.00 | 5.0% |