Chicago Public Schools

MONARCAS

$5.1 million

Exact amount: $5,100,000.00

FY2026 (July 2025–June 2026)

Roof Renovation. Status: Planning. Paid for by: Needs Assessment.

Explore this flow Search this budget →

Follow the money

Inside this box

Pick a rectangle to see what is inside it. Rectangle area shows positive amounts; the complete list includes reductions and tiny amounts.

Where the positive amounts goEach rectangle’s area is proportional to its amount. Select a region to open its box; the list below includes every amount.
MONARCAS: Construction, $4,054,500.00, open this boxMONARCAS: Construction$4.1 millionMONARCAS: Design, $510,000.00, open this boxMONARCAS: Design$510,000MONARCAS: Project management, $280,500.00, open this boxMONARCAS: Project management$280,500MONARCAS: Environmental review, $255,000.00, open this boxMONARCAS: Environmental rev…$255,000

On small screens, use the complete linked table below to explore each box.

All items

Percentages of MONARCAS
BoxAmount% of this budget
MONARCAS: Construction$4,054,500.0079.5%
MONARCAS: Design$510,000.0010.0%
MONARCAS: Project management$280,500.005.5%
MONARCAS: Environmental review$255,000.005.0%

Sources