Chicago Public Schools

KING ES

$4.4 million

Exact amount: $4,380,000.00

FY2026 (July 2025–June 2026)

Roof Renovation. Status: Planning. Paid for by: Needs Assessment.

Explore this flow Search this budget →

Follow the money

Inside this box

Pick a rectangle to see what is inside it. Rectangle area shows positive amounts; the complete list includes reductions and tiny amounts.

Where the positive amounts goEach rectangle’s area is proportional to its amount. Select a region to open its box; the list below includes every amount.
KING ES: Construction, $3,482,100.00, open this boxKING ES: Construction$3.5 millionKING ES: Design, $438,000.00, open this boxKING ES: Design$438,000KING ES: Project management, $240,900.00, open this boxKING ES: Project management$240,900KING ES: Environmental review, $219,000.00, open this boxKING ES: Environmental revi…$219,000

On small screens, use the complete linked table below to explore each box.

All items

Percentages of KING ES
BoxAmount% of this budget
KING ES: Construction$3,482,100.0079.5%
KING ES: Design$438,000.0010.0%
KING ES: Project management$240,900.005.5%
KING ES: Environmental review$219,000.005.0%

Sources