Chicago Public Schools
HUBBARD HS
$7.3 million
Exact amount: $7,300,000.00
FY2026 (July 2025–June 2026)
Roof Renovation. Status: Planning. Paid for by: Needs Assessment.
Follow the money
Inside this box
Pick a rectangle to see what is inside it. Rectangle area shows positive amounts; the complete list includes reductions and tiny amounts.
On small screens, use the complete linked table below to explore each box.
All items
| Box | Amount | % of this budget |
|---|---|---|
| HUBBARD HS: Construction | $5,803,500.00 | 79.5% |
| HUBBARD HS: Design | $730,000.00 | 10.0% |
| HUBBARD HS: Project management | $401,500.00 | 5.5% |
| HUBBARD HS: Environmental review | $365,000.00 | 5.0% |